MIB Structural Homes - Complete Weather Tight Structures in Under 8 Days

Project completed:
Holiday Inn Express, infill project

  • Holiday Inn Express, London
  • Holiday Inn Express, London

Project: Holiday Inn Express, London
Location: London
Type: Leisure/Commercial

Client: Ballast Wiltshire
Area: 3,118m2
Commenced: 2005
Completed: 2005

Scope of Works: Steel frame & MIB MetSIP infill panels. Brick & render cladding.

The panels on each floor were installed prior to the brickwork providing a watertight structure upon installation of the windows. This allowed finishes to commence earlier in the sequence. Holiday Inn Express. Richard Upsall, Ballast Wiltshire.