MIB Structural Homes - Complete Weather Tight Structures in Under 8 Days

Installation timeline

The complete installation of a MIB Structural Home from start to finish is a mere
8 day process which compares favourably with its' blockwork alternative which
is an 8 week process just for wall construction. Click here to view a video demonstration of the MIB Structural Home installation process.

Day 1: Floor track insulated
Day 1: Walls Erected
Day 2: Head track
Day 2: Lintels fitted
Floor joist fitted
Day 3: Floor covering
Day 3: First floor track fitted
Day 3: Stair case installed
Day 4: First floor walls erected
Day 5: Head track fitted
Day 6: Windows installed
Day 7: Roof trusses landed
Day 7: Gable end walls
Day 8: Roof felt and battened
The panels on each floor were installed prior to the brickwork providing a watertight structure upon installation of the windows. This allowed finishes to commence earlier in the sequence. Holiday Inn Express. Richard Upsall, Ballast Wiltshire.